Finsbury Square

Project value: £500,000.00
Time on site: 5 weeks
Size: 80,000 sq ft

Removal of:
– Floor coverings
– Partitions
– Ceilings
– Fixtures and fittings
– Mechanical and electrical incl risers and roof plant
– Client was left with a clean and tidy concrete shell

The client proceeded with the fit out of the building after week 1, whilst we were stripping out, so we had to work closely with them in order to make sure everything run smoothly, efficiently and most importantly, safely.

With difficult access, waste aways were carried out through the night.