Project Profile

Soft strip out works across 3 floors, to take the building back to shell and core leaving the raised floor in place.

Client

Area Ltd

Programme

8 Weeks with all works completed 3 days ahead of schedule

Size & Value

75,000 Sq ft – £235,000.00

Waste Removed

406 Tonnes with 98.5% recycled

Key Works Completed

Removal of:

All floor and ceiling finishes

Partition walls

M & E services

WC areas

Large canteen

Comms areas

Reception area

2 passenger lifts, 1 goods lift

All roof plant

Crew

  • Crew of 22 labourers and 3 SMSTS trained supervisors
  • Sub crews for removal of the roof plant and lifts
  • Designated crew to manage the rubbish removal using the goods lift

Highlights

  • Crane Lift for Large Roof Plant Removal
  • 850 Man Days on Site
  • Accident Free Project
  • Completed ahead of Programme Deadline

“A great job, completed ahead of programme, very safely and with a very hardworking and polite team”

Ben Martin