Project Profile

Removal of Glazed Facade Panels, entrance doors and exterior cladding panels to Front Elevation

Client

Morgan Lovell

Programme

2 Weeks – Completed 2 Days ahead of Schedule

Size & Value

8,500 Sq Ft Facade – £35000.00

Waste Removed

24 Tonnes with 100% recycled

Key Works Completed

Removal of:

Glazed Facade Panels

Entrance doors

Exterior cladding panels

Specific Challenges

Spider Crane with Glass lifting attachment used to remove and lower all glazed panels.

High Levels of Co-ordination with Lawmens Banksmen and operatives with all other site trades and personnel to keep work area clear using exclusion zones.

Completed ahead of Programme Deadline even with weather and bad light delays.

“These works were co-ordinated safely and efficiently with all other trades on site and executed brilliantly by the entire Lawmens Team”

Mark Barnard, Assistant Site Manager